Bloom Roofing, Est. 1979

Case Study · Government

Roof Replacement at the
Theodore Levin U.S. Courthouse

Bloom replaced 44,218 square feet of roofing on Detroit's federal courthouse with an adhered 60-mil Carlisle PVC system, working through a night tear-off, daily security screening and a crawler crane over a closed street. Bloom was later brought back for the light court roofs.

44,218

Square feet replaced

Federal courthouse, downtown Detroit

60-mil

Adhered Carlisle PVC

With APEEL protective film

190 ft

Luffing jib

On a crawler crane with a 170-ft boom

Brought back

Light court roofs

Return work on the lower roof sections

What the Courthouse Required

The Theodore Levin U.S. Courthouse fills a full downtown Detroit block and rises ten stories, with its upper floors built around an open interior light court. Its existing built-up roof needed to be replaced while the courts kept operating below.

The constraints

The work had to respect the building's sensitive internal operations, pass security checkpoints every time crews entered and left, move through an immaculate building without leaving a trace, and deliver a new roof that stayed clean even though the old one was coming off directly beside it.

Why that changes the plan

On an occupied federal building, the schedule is set by the building's rules, not the roofing calendar. Access, screening, lifting and cleanliness had to be planned before the first square foot came off.

The sequence

How the Work Was Sequenced

Every step was planned around a working courthouse in the middle of downtown.

Crawler crane reach

190 feet

Luffing jib on a 170-foot main boom, working over a closed downtown street.

  1. 01

    Tear-off at night

    The old built-up roof came off at night, keeping the dirtiest, noisiest work away from the court's working hours.

  2. 02

    Screened in, screened out

    Crews passed through the building's security checkpoints entering and leaving, every day of the project.

  3. 03

    Lifting from a closed street

    A crawler crane with a 170-foot boom and a 190-foot luffing jib worked from a closed downtown street. A luffing jib changes its angle independently of the main boom, which lets the crane reach up and over the building's edge to place loads on the roof. Materials and equipment were staged below the building.

  4. 04

    Adhered 60-mil Carlisle PVC

    The new white PVC membrane was fully adhered across 44,218 square feet, with curbs, penetrations and roof-to-wall edges flashed into it.

  5. 05

    Peel the film, hand over a clean roof

    The membrane went down with APEEL protective film in place. When the work was complete, the film was pulled off to reveal a clean new roof.

A Clean White Roof Beside a Dirty Tear-Off

Roofer cutting and peeling gray APEEL protective film from the new white PVC membrane at the Theodore Levin U.S. Courthouse.
Peeling APEEL protective film to reveal the finished membrane.

The problem

Tearing off an old built-up roof is dirty work, and a new white membrane shows every footprint and scuff. On this building the clean roof and the tear-off were happening side by side.

The answer: APEEL protective film

Bloom installed Carlisle 60-mil PVC with APEEL protective film, a factory-applied film that covers the membrane surface during installation and guards it from dirt and scuffs. The gray sheets in the project photos are that film. When the work is done, the film is removed and the clean membrane underneath is revealed.

Why it matters to an owner

The roof starts its service life clean and reflective, without pressure washing or chemical cleaning at the end of the job, and without dirty runoff on an immaculate public building.

Brought Back for the Light Court

The courthouse's upper floors wrap around an open interior light court. At the base of that court sit lower roof sections, surrounded on every side by the building above them.

After the main roof replacement, Bloom was brought back to roof those lower sections. On a federal building where every contractor is screened and every schedule is negotiated, being invited back is the most direct reference a building team can give.

Project photos

From the Courthouse Roof

  • Exhaust fan curb flashed into the new PVC membrane, with peeled gray protective film on the roof around it.
  • White membrane roof and rooftop enclosure at the Theodore Levin U.S. Courthouse, with the crane and downtown Detroit towers behind.
  • Overhead view of rooftop units on the new membrane, with sections of gray protective film still in place.
  • Overhead view of the closed street below the courthouse, with crane equipment, dumpsters and staged materials.
  • White membrane roof with walkway pads and a rooftop unit at the Theodore Levin U.S. Courthouse, downtown Detroit.
  • Crew working across the new membrane, seen from above, with sections of gray protective film still in place.
  • Roofing crew working along the roof-to-wall edge at the Theodore Levin U.S. Courthouse in Detroit.
  • Roofer working beside the masonry parapet at the Theodore Levin U.S. Courthouse.
  • Two roofers moving a material cart across the roof at the Theodore Levin U.S. Courthouse.
  • Roofer working beside rooftop piping as gray protective film is pulled back from the new membrane.

The Documented Outcome

The courthouse's built-up roof was replaced with 44,218 square feet of adhered 60-mil Carlisle PVC, and the protective film came off to reveal a clean white roof. The work was completed around the court's operations, security procedures and a downtown street closure.

Bloom was then brought back to roof the lower sections in the light court.

Related: Government roofing · Roof replacement · commercial roofing in Metro Detroit

Roofing an Occupied Public Building?
Start With the Access Plan.

Screening rules, work windows, lifting limits and what has to stay clean. Send us those along with the roof plan, and we will show you how the work can be sequenced before anyone talks membrane.